Agilent 3070 / 79000 Site Preparation
1-4
Chapter 1: Site Preparation – Process: Responsibilities
■
INSURANCE You must provide insurance
coverage for your system from the time it is
delivered to your facility.
■
SOFTWARE SUPPORT CONTRACTS You are
responsible for initiating and renewing support
contracts for software, documentation updates,
and telephone support. Software support and
updates are included during the warranty period.
■
SITE PREPARATION AND MAINTENANCE
You must supply all labor and materials used in
site construction and maintenance. You are also
responsible for obtaining any building permits and
licenses required by local laws and regulations.
■
PROPER USE OF THE SYSTEM You are
responsible for ensuring that use of the system is
consistent with local laws and regulations.
■
UNCRATING You should remove the tri-wall box
from the testhead,
1
but not remove the system
from the pallet. The Agilent representative will
remove the testhead from the pallet. You may
inventory the shipment using the enclosed
packing list. You may leave the smaller boxes for
the Agilent representative to unpack when the
system is installed.
■
INSPECTION You must inspect the system for
physical damage. If you believe that your system
was damaged in shipment, call your Agilent
representative.
■
MOVING Moving the equipment from the
receiving dock to the installation site is the
customers responsibility. The system should be
moved, after the tri-wall box is removed, to an
area safe from damage or misplaced boxes.
■
WIRING AND CABLING Wiring primary power
to the system is your responsibility, as is installing
communications cabling to the system. The actual
power connection to the system will be made after
the CE has removed the system from the pallet
and moved it to the desired location.
1
It will be difficult to remove the tri-wall box in a room with less than 2.5 meters (8 foot) clearance.