ZXR10 8900 Series Hardware Installation Manual
F
IGURE
31 R
EMOVE
T
RUCKLES
1.
Cabinet
2.
Footing
3.
Truckle
4.
Bolt
Loosen the locknuts that fasten the cabinet footings. Place the
cabinet on the adjustable base manually or by lifting machine.
Make sure that the right, left, front and back plane of cabinet
are parallel with the NOC room walls. Use the height adjusting
nut on footing to regulate the height of cabinet. The footing
structure is shown in
Figure 32
.
F
IGURE
32 F
OOTING
S
TRUCTURE
1.
M16 bolt
2.
Locknut
3.
Height Adjusting Nut
4.
Insulated Rubber Pad
2. Cabinet Leveling
The cabinet must be vertically installed. Place level bar on
the two perpendicular directions of cabinet top panel. Use the
height adjusting nut to regulate the horizontality and vertical-
ity of cabinet. Installed horizontality and verticality deviation
must not exceed 3mm. Fasten the locknut upward to fix the
cabinet footing. The fastening torque has to reach 45Nm.
40
Confidential and Proprietary Information of ZTE CORPORATION
Summary of Contents for ZXR10 8900 Series