ZXR10 8900 Series Hardware Installation Manual
F
IGURE
20 I
NSTALLATION
F
LOW OF
B
ASE
D
IRECTLY ON
F
LOOR
Installing Base on Floor Directly
Make sure of base installation position as per standard dimensions
and cabinet dimensions given in layout drawings.
To install base on floor directly, perform the following steps.
1. Marking
Measure the grounding of NOC room with gradienter and make
sure the cabinet will not slant after installation.
Measure some marking points with tape, line two lines which
are parallel to reference and the space is B (for the value of B,
refer to
Table 7
) with ink foundation. According to the design
requirement, define four installation holes of expansion bolts
for installing the first cabinet on these two lines. With this
reference, draw other installation holes of expansion blots.
Positions of single and dual cabinet installation holes are shown
in
Figure 21
and
Figure 22
.
28
Confidential and Proprietary Information of ZTE CORPORATION
Summary of Contents for ZXR10 8900 Series
Page 6: ......