ZXR10 8900 Series Hardware Installation Manual
avoid sway, otherwise the floor will be damaged and hole will
be enlarged and inclined.
Use a vacuum cleaner to remove the dust after drilling.
When floor is too slippery to position drill bit, cut a dent at the
perforation position with punch first to help locating drill bit.
Note:
Marking and drilling are fundamental for hardware installation. In-
accuracy will impact following operations and affect project quality.
Operation quality is essential for ensuring whole project quality.
Result:
Fixed base has been positioned.
Installing Fixed Base
To install fixed base, perform the following steps.
1. Installation of expansion blots
Before installation, clean up dust inside and outside holes with
a vacuum cleaner. Place the base to see if this is aligned with
holes. Expansion bolts must not be installed in holes with large
deviation before re-location and re-drilling is done.
Remove washer and nut (expansion bolt size M12×80) from
expansion bolt, and put expansion bolt and expansion tube into
hole. Strike the expansion bolt with a rubber hammer until the
full expansion tube of the expansion bolt enters the floor.
2. Fixation of base
Clean floor and base surface. Align installation holes on bases
to corresponding expansion bolts, as show in
Figure 29
. Fix
base to the floor with the nuts and washers. Tighten them to
45Nm and adjust horizontality.
F
IGURE
29 I
NSTALLATION OF
B
ASE
1.
Base
2.
Nut
3.
Spring washer
4.
Flat Washer
5.
M12×80 Expansion bolt
36
Confidential and Proprietary Information of ZTE CORPORATION
Summary of Contents for ZXR10 8900 Series