48
DSGH Installation and Operation Guide
Calibration
Before starting the Cal Low data collection:
Check that the correct parameters (vessel inner diameter, engineering
units, measurement span, and source type) are correct.
Power up gauge one hour before start of calibration.
Fill vessel or pipe with low process.
Prepare to draw a sample while the gauge is collecting data.
Procedure 3.4: To set the cal low density
Note:
Perform the data collection for the low and high density within 10
days of each other for a good calibration. The low and high
values must be more than 10% of the process span apart for the
most accurate calibration. Increasing the process span usually
increases the gauge accuracy.
1.
Select
Calibration | 2 Point Calibration | Cal Low Collect
.
2.
Click
Start
.
Summary of Contents for DSGH
Page 2: ......
Page 4: ...2 DSGH Installation and Operation Guide NOTES ...
Page 8: ...6 DSGH Installation and Operation Guide NOTES ...
Page 12: ...10 DSGH Installation and Operation Guide Preface NOTES ...
Page 32: ...30 DSGH Installation and Operation Guide Installation Mounting the DSGH gauge ...
Page 56: ...54 DSGH Installation and Operation Guide Calibration NOTES ...
Page 94: ...92 DSGH Installation and Operation Guide Diagnostics and repair NOTES ...
Page 98: ...96 DSGH Installation and Operation Guide NOTES ...
Page 99: ......