f. Multiple individual boiler vertical vent pipes
may be piped through a common conduit or
chase so that one roof penetration may be made.
g. For vertical roof terminations, maintain at
least 12 in. (300 mm) minimum horizontal
distance between adjacent individual boiler vent
terminations.
2. Combustion Air Piping
a. Multiple boiler combustion air terminations are
shown in Figure 23.
iV. Venting
G. Multiple Boiler Installation Venting (continued)
b. Each individual boiler must have own
combustion air pipe and terminal. Refer to
Paragraphs A through F (as applicable) for
individual boiler combustion air guidelines and
options.
c. Do not exceed the individual boiler maximum
combustion air pipe length listed in Table 8.
d. If possible, locate vent and combustion air
terminals for an individual boiler on the same
wall to prevent nuisance shutdowns. If not,
an individual boiler may be installed with a
roof vent terminal and sidewall combustion air
terminal.
Summary of Contents for Alpine ALP500C
Page 48: ...48 VI Water Piping and Trim continued Figure 28 Near Boiler Piping Heating Only ...
Page 62: ...62 Figure 40 Ladder Diagram VIII Electrical continued ...
Page 63: ...63 VIII Electrical continued 2 Figure 41 Wiring Connections Diagram ...
Page 72: ...72 IX System Start up continued Figure 48 Operating Instructions ...
Page 124: ...124 XIII Repair Parts continued ...
Page 126: ...126 XIII Repair Parts continued ALP600C ALP700C and ALP800C ALP800C shown ...
Page 130: ...130 XIII Repair Parts continued ...
Page 133: ...133 XIII Repair Parts continued 10A 10B 10C 10D 10G ...
Page 143: ...143 ...
Page 144: ...144 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net ...