a. Plan venting system to avoid possible contact
with plumbing or electrical wires. Start at
vent connector at boiler and work towards vent
termination.
b. Design the vent system to allow 3/8 in.
(9.5 mm) of thermal expansion per 10 ft. (3.0 m)
of CPVC/PVC pipe. Runs of 20 ft. (6.1 m) or
longer that are restrained at both ends must use
an offset or expansion loop. Refer to Figure 14
and Table 15.
c. All CPVC/PVC vent and combustion air
pipe joints must be cleaned with primer and
glued with cement. Follow all manufacturer
instructions and warnings when preparing pipe
ends for joining and using the primer and the
cement.
5. Horizontal Sidewall Termination
a. Standard Two-Pipe Termination
See Figure 7.
i.
Vent Piping
Running PVC vent pipe inside Enclosures
and through Walls:
• PVC vent pipe must be installed in such
way as to permit adequate air circulation
around the outside of the pipe to prevent
internal wall temperature rising above
ANSI Z21.13 standard specified limit.
• Do not enclose PVC venting. Use higher
temperature rated CPVC pipe in enclosed
spaces or to penetrate combustible or
non-combustible walls.
Summary of Contents for Alpine ALP500C
Page 48: ...48 VI Water Piping and Trim continued Figure 28 Near Boiler Piping Heating Only ...
Page 62: ...62 Figure 40 Ladder Diagram VIII Electrical continued ...
Page 63: ...63 VIII Electrical continued 2 Figure 41 Wiring Connections Diagram ...
Page 72: ...72 IX System Start up continued Figure 48 Operating Instructions ...
Page 124: ...124 XIII Repair Parts continued ...
Page 126: ...126 XIII Repair Parts continued ALP600C ALP700C and ALP800C ALP800C shown ...
Page 130: ...130 XIII Repair Parts continued ...
Page 133: ...133 XIII Repair Parts continued 10A 10B 10C 10D 10G ...
Page 143: ...143 ...
Page 144: ...144 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net ...