Spike Systems: PBG System Family Installation
39
3.4 Replace Inside Panels for Control and Non-‐Control Cabinets
At this time, replace the inner panels of both the Control and Non-‐Control Cabinets
as shown in the figure below.
Figure 43 – Replacement of Inner Panels Control and Non-Control Cabinets
Tool Required
Tool Type
Tool Specification
Wrench/Socket
7/16 “
3.5 AC Power Connection
The client-‐supplied power is to be connected to the 4-‐gang junction box via flexible conduit.
The flexible conduit and power wires are to be routed through the bottom of the junction
box in the location shown in the photo below. Local code may require that a licensed
electrical contractor perform this step.
NOTE
– The Switch on the 4-‐gang junction box, when switched to the ON position, allows
power to flow to the Spike system from the AC power source.
Summary of Contents for PBG Series
Page 8: ...Spike Systems PBG System Family Installation vi...
Page 22: ...Spike Systems PBG System Family Installation 14 INTENTIONALLY BLANK...
Page 56: ...Spike Systems PBG System Family Installation 48 Figure 54 Siemens PLC Wiring Scheme...
Page 68: ......
Page 82: ...Spike Systems PBG System Family Installation 74...
Page 84: ......
Page 90: ...Spike Systems PBG System Family Installation 82...
Page 91: ...Spike Systems PBG System Family Installation 83...
Page 92: ...Spike Systems PBG System Family Installation 84...
Page 93: ...Spike Systems PBG System Family Installation 85...
Page 94: ...Spike Systems PBG System Family Installation 86...