5-100
DNW-A100/A50/A45
DNW-A100P/A50P/A45P
5-15. Brake Solenoid Replacement
Outline
Replacement
1.
Reel Table Assembly Removal
2.
Crank Arm and Slide Shaft Support Removal
3.
RS Table Block Assembly Removal
4.
Harnesses Disconnection (CN926 and CN927 on RM Board)
5.
Reel Motor Assembly Removal
6.
Brake Assembly Removal
7.
Brake Solenoid Removal
8.
Brake Solenoid Installation
9.
Brake Assembly Installation
10. Cleaning (Reel Motor Assembly)
11. Reel Motor Assembly Installation
12. Harnesses Connection (CN926 and CN927 on RM Board)
13. Flat Cable Connection
14. Slide Shaft Installation
15. RS Table Block Assembly Installation
16. Applying Grease to Slide Shaft
17. Crank Arm Installation
Adjustment after Replacement
18. Reel Motor Shaft Slantness Confirmation (Refer to Section 5-9-2.)
19. Reel Table Assembly Installation
20. Cassette Holder Post Height Confirmation (Refer to Section 5-9-3.)
21. Reel Table Height Confirmation (Refer to Section 5-9-4.)
22. Reel Brake Clearance Confirmation (Refer to Section 5-9-5.)
23. Reel Brake Release Confirmation (Refer to Section 5-9-6.)
24. Brake Solenoid Operation Confirmation (Refer to Section 4-2-2 in Mainte-
nance Manual Part 1.)
(C021: S REEL BRAKE, C022: T REEL BRAKE)
5-15. Brake Solenoid Replacement