10
5.1. Installation of pipes and fume exhaust
systems:
The exhaust pipe must have been designed for this purpose, in
compliance to the location requirements and in accordance with any
applicable regulations.
Important! An inspection-"T", fitted with a hermetic lid, must be
attached to the end of the boiler's exhaust pipe to allow for the regular
inspection of the system, as well as the discharge of heavy dust and
condensates.
As indicated in Figure 4, the exhaust duct must be assembled so as to
permit its cleaning and maintenance through the inspection points
.
Under normal operating conditions, the combustion gas flow should
create a draught of 12 Pa one meter above the chimney neck.
The boiler must not share the chimney with any other equipment.
The pipes located outside the boiler's working area must have an
internal diameter of 100 mm and be of double stainless steel insulation.
The fume exhaust pipe may generate condensation, so we
recommend that the appropriate systems for collecting
condensates should be installed.
5.2. Installation without a shaft
Figure 5 and 6 illustrate the basic requirements when installing the boiler's
chimney. A "T" should be included at the base of the piping system for the
purpose of periodic inspections and annual maintenance, as exemplified.
Double-walled stainless steel insulated pipes must be used and properly
fastened to avoid condensation.
Summary of Contents for SZM A 18 KW
Page 15: ...12 b c Figure 6 Examples of standard installations ...
Page 50: ...47 a b Figure 27 b and c a b ...
Page 82: ...79 Figure 68 Electrical diagram of the external silo s circuit board ...
Page 87: ...84 ...
Page 88: ...85 ...
Page 89: ...86 ...