Introduction
This chapter provides instructions for installing and removing the Extreme Edge Server in
a rack or cabinet. It also provides information and procedures for grounding, powering up
and down, and disconnecting the server from the power feed.
4.2
Before Installation
Refer to
for location of LEDs, connectors and earth ground point.
Before you start the installation, make sure that you have all of the necessary equipment
and tools available.
Provide the following cables:
Earth grounding cable with an M4 ring lug in case of rack installation
Twisted pair Ethernet cable for connecting the BMC ETH
Twisted pair Ethernet cable for the front panel ETH1 and ETH2 RJ-45 ports
SFP+ or SFP modules or direct connect copper cables for the five SFP+ ports
The connectivity of the RJ-45 ports to CPU1 and/or CPU2 is covered in
and
Section 1.7.2.2, PCIe-Based Gigabit Ethernet on page 57
4.3
Install the Extreme Edge Server in the Cabinet
For installation recommendations regarding outside installations, go to
Usage
Equipment and Tools
General
Torque wrench
ESD wrist strap
Server / Rack / Cabinet Four bolts or screws 6mm / 0.24" diameter
Grounding
Ground cable 1.25 mm
2
for DC system
Power
DC power cable
System Access
USB Type-A to USB Type-A cable
PC or laptop
Summary of Contents for MC1600
Page 1: ...MC1600 Extreme Edge Server Installation and Use P N 6806870A02B January 2020...
Page 8: ...List of Figures 8 MC1600 Extreme Edge Server Installation and Use 6806870A02B...
Page 24: ...24 MC1600 Extreme Edge Server Installation and Use 6806870A02B Safety Notes Safety Notes...
Page 125: ...1...