Installing
3.2 EMC-compliant installation of a machine or system
Power Module PM240-2
26
Hardware Installation Manual, 01/2020, A5E33294624B AL
Figure 3-3
Routing converter cables inside and outside a control cabinet
Routing cables outside the control cabinet
●
Maintain a minimum clearance of 25 cm between cables with a high level of interference
and cables with a low level of interference.
●
Use shielded cables for the following connections:
–
Converter motor cable
–
Cable between the converter and braking resistor
–
Signal and data cables
●
Connect the motor cable shield to the motor enclosure using a PG gland that establishes
a good electrical connection.
Summary of Contents for SINAMICS G120
Page 1: ...Power Module PM240 2 ...
Page 2: ......
Page 6: ...Preface Power Module PM240 2 4 Hardware Installation Manual 01 2020 A5E33294624B AL ...
Page 10: ...Table of contents Power Module PM240 2 8 Hardware Installation Manual 01 2020 A5E33294624B AL ...
Page 118: ...Spare parts Power Module PM240 2 116 Hardware Installation Manual 01 2020 A5E33294624B AL ...
Page 175: ......
Page 176: ......