Configuration in STEP 7
5.1 Overview
TIM DNP3
System Manual, 12/2015, C79000-G8976-C253-04
79
Following each step, the configured data must be saved.
As the second to last step, the subscriber information, the system data blocks (SDBs) are
generated for TIM and CPU modules.
Finally, the SDBs are downloaded to the relevant modules.
5.1.3
Configuration of a TIM - overview
Introduction
The next sections provide you with a brief summary of configuration and parameter
assignment and explain which data generated during commissioning needs to be loaded on
the TIM to make it operational.
The individual steps are described in detail in the sections that follow.
Configuration in STEP 7 V5.5
As with all other S7 modules, the configuration of the TIM is performed in the STEP 7 HW
Config program. The various TIM modules can be found there in the hardware catalog in the
SIMATIC 300 / SINAUT ST7 folder.
You can select the TIM you want to install in a rack from this catalog. The following figure
shows an S7-300 station with a TIM and various other modules installed.
Summary of Contents for SIMATIC TIM 3V-IE DNP3
Page 12: ...Table of contents TIM DNP3 12 System Manual 12 2015 C79000 G8976 C253 04 ...
Page 311: ...Approvals TIM DNP3 System Manual 12 2015 C79000 G8976 C253 04 311 ...
Page 312: ......
Page 350: ...Glossary TIM DNP3 350 System Manual 12 2015 C79000 G8976 C253 04 ...
Page 354: ...Index TIM DNP3 354 System Manual 12 2015 C79000 G8976 C253 04 ...