Installation
The transport holes for pushing the lifting rods in are marked on the transport unit with
a red symbol.
➭ If necessary, remove the switchgear termination.
➭ Push the lifting rods into the transport holes at the front and at the rear.
➭ Attach ropes or chains at the ends of the lifting rods.
➭ Stretch the ropes or chains by lifting the hoisting tackle carefully.
➭ If the ropes or chains are touching the transport unit, use transport tackle/expander.
➭ Lift the transport unit carefully.
➭ Lif the transport unit by means of a crane.
Fig. 33:
Position of transport holes
Fig. 34:
Marking of transport holes
Fig. 35:
Example for craning the transport unit
①
1037 mm (height of switchgear dependent on built-on components)
②
462 mm