16 - 140
Installation Guidelines
Figure 3-2 Installation
(1) Locate the position of the installation hole.
(2) Fix the screw or nut on the located position.
(3) Put the inverter against the wall.
(4) Tighten up the screws.
3.2 Standard wiring
3.2.1 Connection diagram of main circuit
Figure 3-3 Connection diagram of main circuit
Note:
The circuit breaker, braking resistor, input reactor, input filter and output filters are optional parts.
Please refer to
Peripheral Optional Parts
for detailed information.
Remove the yellow warning labels of PB, (+) and (-) on the terminals before connecting the
braking resistor; otherwise poor connection may occur.