SECTION 5
Pronar T743
5.15
IMPORTANT!
Travel with unreliable lighting and signalling system is forbidden. Damaged lamp lenses,
and burned-out bulbs must be replaced before travelling.
Checking technical condition of electrical system:
•
daily,
•
every 12 months of use.
Annual inspection of system does not relieve user of daily checking of technical condition of
lighting system.
5.2.11 OPERATION 11- CHECKING NUT AND BOLT TIGHTNESS ON WHEELS
AND DRAWBAR
Wheel nuts should be tightened using a torque of 450 Nm. Inspection of nut and bolt
tightness should take place each time after first use, after first journey with a load and then
every 6 months of trailer use. In the event of intensive work checking the nut tightening
should be done at least every 100 km.
FIGURE 5.5
Tightening wheels nuts
(1) - (10) sequence of nut tightening, (L) spanner length, (F) user weight
Summary of Contents for T743
Page 2: ......
Page 6: ......
Page 11: ......
Page 12: ...SECTION 1 BASIC INFORMATION ...
Page 25: ...Pronar T743 SECTION 1 1 14 ...
Page 26: ...SECTION 2 SAFETY ADVICE ...
Page 46: ...SECTION 2 Pronar T743 2 21 FIGURE 2 3 Locations of information and warning decals ...
Page 47: ...Pronar T743 SECTION 2 2 22 ...
Page 48: ...SECTION 3 DESIGN AND OPERATION ...
Page 80: ...SECTION 4 CORRECT USE ...
Page 99: ...Pronar T743 SECTION 4 4 20 ...
Page 100: ...SECTION 5 MAINTENANCE ...
Page 119: ...Pronar T743 SECTION 5 5 20 FIGURE 5 6 Trailer lubrication points chassis ...
Page 120: ...SECTION 5 Pronar T743 5 21 FIGURE 5 7 Trailer lubrication points vertical conveyor ...
Page 147: ...Pronar T743 SECTION 5 5 48 ...
Page 148: ...NOTES ...
Page 149: ... ...