Use, maintenance and warning instructions
MEDIUM PRESSURE REGULATOR
|
COMMISSIONING
|
REV. 00
8.6 - COMMISSIONING PROCEDURE FOR THE REGULATOR REVAL 182 WITH
PM 182 INCORPORATED MONITOR
Fig. 8.33.
Procedure for commissioning the regulator REVAL 182 with PM/182 built-in monitor
Step
Action
1
Partially open the drain cock (6).
2
Completely unscrew the nut securing the adjusting screws (fig. 8.43) of the pilots (3, 10).
3
Completely compress the pilot spring (3) by turning the adjusting screw (fig. 8.43) clockwise.
4
Completely relieve the pilot spring (10) by turning the adjustment screw (fig. 8.43) anticlockwise.
5
Open the inlet shut-off valve (V1) very slowly.
NOTICE!
Check the pressure by referring to the pressure gauge (4) located upstream.
6
Turn the adjustment screw (fig. 8.43) on the monitor pilot (10) clockwise to increase the downstream pressure
value to the selected monitor operating value.
NOTICE!
Check the pressure referring to the pressure gauge (5) located upstream.