114
REV
AL 182
EN
Use, maintenance and warning instructions
MEDIUM PRESSURE REGULATOR
|
COMMISSIONING
|
REV. 00
8.11 - COMMISSIONING PROCEDURE FOR THE REGULATOR REVAL 182 WITH
HB/97 SLAM-SHUT VALVE
8.11.1 - CHECKING THE SB/97 SLAM-SHUT VALVE FOR SEALING DURING SHUT-OFF
Fig. 8.40.
Sealing of the HB/ 97 slam-shut valve during shut-off
Step
Action
1
Check that the slam-shut valve is in the shut-off position.
2
Open the drain cock (6) and drain the downstream section completely.
3
Slowly open upstream valve V1.
4
Check the tightness of the slam-shut valve through the pilot circuit supply connection located under the regu-
lator head, disconnecting the connection from the regulator.
NOTICE!
•
Check the seal with a foaming substance;
•
If the connection is leaking, refer to chapter 10 “Fault search and troubleshooting” to re
-
move the causes of the malfunction.
5
Reconnect the power connection of the drive circuit.
NOTICE!
Check whether to replace the fitting by referring to the fitting manufacturer’s instructions.
Tab. 8.82.
Summary of Contents for REVAL 182
Page 404: ......