8.3.2 Single GEO S12 rigidly mounted on a wall or a ceiling (vertical or horizontal)
Required items
•
1 x GEOS12-UBRK (allows all angles to be implemented)
•
4 x 12mm diameter screws (
not provided
)
IMPORTANT
Ensure that the surface – wall or ceiling – is strong enough to hold GEO S12 weight and
that the for screws 12mm diameter and corresponding plugs required to fix the “U”
bracket on the wall or under the ceiling are properly dimensioned.
Procedure
•
For screws 12mm diameter (not provided) are required to secure the “U” Bracket on the wall or
ceiling;
•
Remove the four TORX screws holding connector plates on both sides of GEO S12;
•
Fill each screw hole with Locktite 243 or equivalent;
•
Position the GEO S12 inside the “U” Bracket to desired angle; “U” bracket oblong holes must be
properly aligned with panels holes;
•
Use the eight screws and washers from GEOS12-UBRK kit to connect “U” bracket to cabinet.
Summary of Contents for GEO S12 Series
Page 48: ...Page 48 112 GEO S12 HARDWARE SETUP PROCEDURE ...
Page 52: ...Page 52 112 GEO S12 HARDWARE SETUP PROCEDURE ...
Page 54: ...Page 54 112 GEO S12 HARDWARE SETUP PROCEDURE DOWN CABINET UP CABINET ...
Page 66: ...Page 66 112 GEO S12 HARDWARE SETUP PROCEDURE ...