8.3.7 GEO S12 horizontal array cable mounted on a ceiling
Required items
•
2 x GEO S12-LBRK (allows cable suspension for horizontal arrays, holes for cable suspension
are 10mm diameter);
•
(N-1) x GEOS12-ANPL for a N x GEO S12 array (ANPL1 ranges from 0.2° to 3.15°, ANPL2
ranges from 5° to 10°, ANPL3 ranges from 16° to 30°)
•
4 slings and 4 shackles (not provided).
IMPORTANT
Ensure that the ceiling is strong enough to hold GEO S12 cluster weight and that the
cables suspension system required fixing the cluster under the ceiling is properly
dimensioned.
Procedure
•
Proceed as in above section, GEOS12-LBRK being positioned on the outer cabinets instead of
GEOS12-ABRK.
•
4 slings and 4 shackle (not provided) are required to secure the cluster under the ceiling;
Summary of Contents for GEO S12 Series
Page 48: ...Page 48 112 GEO S12 HARDWARE SETUP PROCEDURE ...
Page 52: ...Page 52 112 GEO S12 HARDWARE SETUP PROCEDURE ...
Page 54: ...Page 54 112 GEO S12 HARDWARE SETUP PROCEDURE DOWN CABINET UP CABINET ...
Page 66: ...Page 66 112 GEO S12 HARDWARE SETUP PROCEDURE ...