Indoor unit
10. Installation
Ceiling Concealed Duct(Middle Static)
_
37
Indoor Units
10.2 Ceiling dimension and hanging
bolt location
n
Installation of Unit
Install the unit above the ceiling correctly.
• Apply a joint-canvas between the unit and duct to absorb
unnecessary vibration.
• Install the unit leaning to a drainage hole side as a figure
for easy water drainage.
• A place where the unit will be leveled and that can sup-
port the weight of the unit.
• A place where the unit can withstand its vibration.
• A place where service can be easily performed.
POSITION OF SUSPENSION BOLT
C
E
G
D
F
I
A
J
B
H
Drain hole
M10 Nut
M10 washer
X 4
X 4
M10 Nut
M10 washer
X 4
X 8
NOTE:
• Throughly study the following installation locations:
1. In such places as restaurants and kitchens, considerable amount of oil steam and flour adhere to the fan, the fin of
the heat exchanger, resulting in heat exchange reduction, spraying, dispersing of water drops, etc.
In these cases, take the following actions:
• Make sure that the ventilation fan for smoke-collecting hood on a cooking table has sufficient capacity so that it
draws oily steam which should not flow into the suction of the air conditioner.
• Make enough distance from a cooking room to install the air conditioner in such a place where it may not suck in
oil steam.
2. Avoid installing air conditioner in such circumstances where cutting oil mist or iron powder is in suspension in facto-
ries, etc.
3. Avoid places where inflammable gas is generated, flows in, is stored or vented.
4. Avoid places where sulfurous acid gas or corrosive gas is generated.
5. Avoid places near high frequency generators.
(Unit:mm)
Dimension
A
B
C
D
E
F
G
H
I
J
Chassis name
M1
933.4 971.6 619.2
700
30
270
15.2
858
201.4
900
M2
1283.4 1321.6 619.2
700
30
270
15.2
1208 201.4 1250
M3
1283.4 1321.6 619.2
700
30
360
15.2
1208 291.4 1250