2.9 Installation of the flowmeter
2.9.1 General mechanical installation
Installation of the rails with the metal straps
Installation of the rails with the metal straps
Installation of the rails with the metal straps
Installation of the rails with the metal straps
•
1
guide one end of the metal strap through the lower strap lock on both the side of the sensor
rail
2
.
•
3
+
4
wrap both metal strap around the piping.
•
5
return the other end of the metal strap through the upper strap lock on both the side of the
sensor rail
2
.
•
6
tighten and lock the strap locks with an Allen wrench.
i
Both sides from sensor rail are secured on the piping