Page 30
EN
Chapter 7 Commissioning
15. Turn the start switch to “0”. The machine will stop.
16. Switch on the compressor and turn the start switch
back to “PNEU”. From now on, the machine is switched
on and off via the air valve on the spray head.
17. First of all, open the material lever on the spray head
and then the air valve. The actual spraying process
starts. Check the mortar pressure gauge to see if the
mortar pressure is within the permissible range.
18. Process the existing material (e.g. spray-on filling com-
pounds on a wall), with a second worker continuously
filling the material container with bagged goods.
7 Commissioning
7.1 Adding material to the material hopper
Warning
Risk to health due to dust.
When cleaning the machine, inhaled dust can cause
long-term lung damage or other adverse health ef-
fects.
• The machine operator or people working in the dust area
must each wear a dust mask when cleaning the machine.
• Find out about the technical rules for hazardous sub-
stances (TRGS 559) “Mineral dust” on the homepage of
the German Social Accident Insurance Institution (www.
bgbau.de).
Warning
Risk of injury posed by powdery and paste-
like material
When adding bagged goods to the material hopper, swirl-
ing or splashing material may pose a risk of injury, espe-
cially in the region of the eye and face.
• Always wear safety goggles.
7.2 Opening and emptying bags of material
Warning
Observe the applicable occupational safety
regulations (e.g. respiratory protection)
To clean the bags of material, proceed as follows:
1. Place the bag of material on the hopper mesh with the
tooth rail.
2. Tear open the bag of material by using short forward and
backward movements.
3. Move the bag sideways and upwards and then empty
the contents into the material hopper.
4. Observe the applicable occupational safety regulations
(e.g. respiratory protection, etc.).
5. Dispose of the empty bags of material and other pack-
aging material in an environmentally friendly manner in
accordance with the instructions provided by the packag-
ing manufacturer.
Summary of Contents for inoCOMB Picco Power
Page 41: ...Page 41 EN Chapter 13 Systems 13 3 Circuit diagram for compressor...
Page 42: ...Page 42 EN Chapter 13 Systems 13 3 1 Circuit diagram for mixer motor safety switch...
Page 44: ...Page 44 EN Chapter 13 Systems 13 3 3 Circuit diagram for pump rotation speed...
Page 45: ...Page 45 EN Chapter 13 Systems 13 3 4 Switching cabinet subplate inside...
Page 46: ...Page 46 EN Chapter 13 Systems 13 3 5 Switching cabinet outside...