TL unit electrical diagram
For Ingecon
®
μWind 2.5TL, 3TL, 3.3TL, 3.68TL, 4.6TL, 5TL and 6TL.
wind generator
thermomagnetic
circuit breaker
Electricity company panel
counter
kWh
grid
inverter
Electrical diagram for units with transformers
For Ingecon
®
μWind 2.5, 3.3 and 5.
wind generator
thermomagnetic
circuit breaker
transformer
Electricity company panel
counter
kWh
grid
inverter
Electrical wiring diagram for TL equipment with a connection to Ingecon
®
μWind Interface (IWI)
For Ingecon
®
μWind 2.5TL, 3TL, 3.3TL, 3.68TL, 4.6TL, 5TL and 6TL with a connection to Ingecon
®
μWind Interface.
wind generator
thermomagnetic
circuit breaker
Electricity company panel
IWI
inverter
counter
kWh
grid
Electrical wiring diagram for transformers with a connection to Ingecon
®
μWind Interface (IWI)
For Ingecon
®
μWind 2.5, 3.3 and 5 with a connection to Ingecon
®
μWind Interface.
wind generator
thermomagnetic
circuit breaker
transformer
Electricity company panel
IWI
counter
kWh
grid
inverter
5.3.4. Multi-purpose access
The orifices provided for this function can be opened by breaking the knock-out in the unit’s base. Once the orifices
have been opened, they must be fitted with M12 and/or M20 metric cable glands which accept pipes of a diameter
between 3.5 and 7 mm for M12 and between 7 and 13 mm for M20.
Once the connection has been made, check that the cable glands used have been properly fitted to guarantee sealing
of the box.
A closure which is not sealed may allow moisture to enter and seriously damage the unit, invalidating the manufac-
turer’s warranty in addition.
If a knock-out which is not to be used is opened accidentally or one which has been fitted with a cable gland is no
AAY2000IKI04
31
Installation manual
Ingeteam Power Technology, S.A.
Summary of Contents for Ingecon mWind 2.5
Page 1: ...Ingecon Wind Installation manual...
Page 55: ...Notes...