12
1 Installation Holes for the Subrack
1
2
82
83
Scenario
Component
Installation Holes
Remarks
2 x T32
subracks
(One
electrical
subrack at
most)
PDU
81, 83
-
T32
44, 46, 58, 59, 74, 76
If only one T32
subrack needs to
be installed,
install the subrack
in the top-most
area of the
cabinet. Note that
the cabinet must
stand vertically
after the subrack
is installed.
T32
7, 9, 21, 22, 37, 39
DCM
1, 2
-
2 x T32
electrical
subracks
PDU
81, 83
-
T32
77, 75, 60, 59, 47, 45
-
Air deflector
40, 39
-
T32
37, 35, 20, 19, 7, 5
-
1 x T32
s
2 x 6800
subracks
PDU
81, 83
-
T32
44, 46, 58, 59, 74,
76
-
6800 subrack
24, 25, 38, 39
-
6800 subrack
8, 9, 22, 23
-
DCM
1, 2, and 3, 4
-
1 x T32
s
2 x T16
subracks
PDU
81, 83
-
T32
45, 47, 59, 60, 75,
77
-
T16 subrack
24, 25, 38, 40
-
T16 subrack
6, 7, 20, 22
-
DCM
1, 2
-
1 x T32
s
2 x
universal
platform
subracks
PDU
81, 83
-
T32
44, 46, 58, 59, 75,
76
-
Universal
platform
subrack
24,25,38,39
-
Universal
platform
subrack
8,9,22,23
-
DCM
1, 2, and 3, 4
-
Deploying T32 Subracks or T32 and Other Subracks in the Same N63B Cabinet
b
The installation holes on an N63B cabinet are numbered 1 to 83 from bottom to top.
Installation holes on an N63B cabinet
Front side of an N63B cabinet