2 Unit installation
KPI energy and KPI active unit
SMGB0099 rev.0 - 12/2016
69
2
Prepare the sling bolts.
Fit the anchor bolts on the suspension bracket and adjust to ensure the unit is installed horizontally.
Thread on the nuts and fit the washers for all the bolts, as shown in the figure.
Fit two suspension brackets onto the nut and washer of each bolt, starting on one side.
Check that the nuts and washers are correctly secured with the suspension bracket retainers and fit the brackets onto
their nuts and washers on the other side.
Anchor bolt
(M10 or M12)
Nut
Nut
Washer
Rubber isolator
!
C A U T I O N
The unit control box is fragile. Do not apply force to the control box.
Where the sling bolts are too short, fit the suspension bracket in an alternative position.
1 Remove the bolts from the upper installation position.
2
Remove the suspension brackets and fit in a higher
installation position.
3 Tighten the bolts in the holes from which the
suspension brackets have been removed to avoid air
leaks.
KPI unit
5 mm
Nut
Washer
Anchor bolt
Rubber isolator
!
C A U T I O N
•
Before lifting the unit, prepare any necessary means (ladders, scaffolding, elevator platform, etc.) and check that the current safety
regulations in the place where the installation is taking place are met.
•
Check that the lifting work can be carried out without the risk of injuries to you or others in the surrounding area.
• Request the assistance of another person to lift the unit.
Lift the unit carefully.
For KPI-(502-1002)X4E
The unit should be installed so that one side of the unit is slightly 1º for KPI-(502-1002)X4E lower than the other side, in
order to avoid the incorrect position of the drain discharge.
Apply a thread-locking product to the bolts and nuts to prevent them from loosening. Otherwise, abnormal noise may be
caused by mechanical vibrations and the indoor unit may become loose.
Apply protective paint to the bolts and nuts to prevent rusting.
!
C A U T I O N
Completely cover the unit with a sheet of plastic to protect it during installation work.