3-17
3.8 Vertical milling
• Close the front and lateral enclosure doors.
• Select the operating mode "Manual".
• Position the spindle by entering the M-function M
29. The axis moves to the best mounting position
and the screen shows the message "PROTECTIVE
COVER".
• The front enclosure doors are released
automatically. Open them as far as possible.
• Remove the large protective cover [4] .
• Message of the TNC "SWIVEL OUT V-HEAD".
• Thorougly clean the fastening surfaces to remove
dirt and coolant lubricant and slightly oil them with
an acid-free oil before swivelling out the vertical
milling head.
• Turn the release lever [3] to the left and pull the
vertical milling head forward until it engages.
• Slowly swivel the milling head by 90° to the
downside, until the fastening surfaces are parallel.
• Turn the release lever to the left, push the vertical
milling head strongly against the front of the spindle
slide and tighten the four fastening screws [2].
• The message "Swivel out the V-head" disappears
• The machine is switched over to the vertical spindle
by pulling the V-head out of its parking position. .
• Attach the small protective cover [1] to the four pins
[5] .
Note
Never turn at the spindle when swivelling in or out, as
this will change the spindle position from the V-head
to the spindle and the V-head cannot be swivelled out.
If the EMERGENCY OFF is operated while swivelling
in or out the V-head , please note the message of the
TNC.
If your machine has a hydraulic clamping (optional
available) screwing and unscrewing of the fastening
screws is not necessary.
Horizontal Milling
Intermediate position
Vertical Milling
3
5
4
1
2
3.8
Summary of Contents for UWF 902 H
Page 1: ...Universal Toolroom Milling and Boring Machine Operating Manual UWF 902 H ...
Page 2: ...1 2 3 4 5 12 13 15 14 9 10 11 8 7 16 6 17 ...
Page 4: ...Control TNC 426 ...
Page 30: ...2 11 2 2 7 Preparation for Initial Start Up 4 1 ...
Page 64: ...4 2 4 1 2 Technical Data Tool Changer Tool changing horizontal Tool changing vertical ...
Page 74: ...4 12 0 450 180 18 468 30 85 10 465 47 63 14 H7 ca 245 ca 470 ca 75 208 0 500 73 92 4 2 2 ...
Page 91: ...4 29 4 4 5 1 Cover plate 2 Recess 3 Taper pin 4 Hand crank ...