69
HEIDENHAIN TNC 426 B, TNC 430
5.2 Tool Data
You usually program the coordinates of path contours as they are
dimensioned in the workpiece drawing. To allow the TNC to
calculate the tool center path — i.e. the tool compensation — you
must also enter the length and radius of each tool you are using.
Tool data can be entered either directly in the part program with
TOOL DEF or separately in a tool table. In a tool table, you can also
enter additional data on the specific tool. The TNC will consider all
the data entered for the tool when executing the part program.
Tool numbers and tool names
Each tool is identified by a number between 0 and 254. If you are
working with tool tables, you can use higher numbers and you can
also enter a tool name for each tool.
The tool number 0 is automatically defined as the zero tool with the
length L=0 and the radius R=0. In tool tables, tool 0 should also be
defined with L=0 and R=0.
Tool length L
There are two ways to determine the tool length L:
1
The length L is the difference between the length of the tool and
that of a zero tool L
0
.
For the algebraic sign:
■
The tool is longer than the zero tool
L>L
0
■
The tool is shorter than the zero tool:
L<L
0
To determine the length:
ú
Move the zero tool to the reference position in the tool axis
(e.g. workpiece surface with Z=0).
ú
Set the datum in the tool axis to 0 (datum setting).
ú
Insert the desired tool.
ú
Move the tool to the same reference position as the zero tool.
ú
The TNC displays the difference between the current tool and the
zero tool.
ú
Enter the value in the TOOL DEF block or in the tool table by
pressing the actual-position-capture key.
2
Determine the tool length L with a tool presetter. This allows you
to enter the determined value directly in the TOOL DEF tool
definition block or in the tool table without further calculations.
5.2 T
ool D
ata
Z
X
L
0
Fkap5.pm6
30.06.2006, 07:03
69
www.EngineeringBooksPdf.com
Summary of Contents for TNC 426 B
Page 3: ...BAUSKLA PM6 30 06 2006 07 03 2 www EngineeringBooksPdf com ...
Page 4: ...BAUSKLA PM6 30 06 2006 07 03 3 www EngineeringBooksPdf com ...
Page 6: ...CINHALT PM6 30 06 2006 07 03 2 www EngineeringBooksPdf com ...
Page 16: ...CINHALT PM6 30 06 2006 07 03 12 www EngineeringBooksPdf com ...
Page 17: ...Introduction 1 Dkap1 pm6 30 06 2006 07 03 1 www EngineeringBooksPdf com ...
Page 29: ...Manual Operation and Setup 2 Dkap2_3 pm6 30 06 2006 07 03 13 www EngineeringBooksPdf com ...
Page 83: ...Programming Tools 5 Fkap5 pm6 30 06 2006 07 03 67 www EngineeringBooksPdf com ...
Page 106: ...Fkap5 pm6 30 06 2006 07 03 90 www EngineeringBooksPdf com ...
Page 107: ...Programming Programming Contours 6 Gkap6 pm6 30 06 2006 07 04 91 www EngineeringBooksPdf com ...
Page 165: ...Hkap7 pm6 30 06 2006 07 03 150 www EngineeringBooksPdf com ...
Page 166: ...Programming Cycles 8 kkap8 pm6 30 06 2006 07 03 151 www EngineeringBooksPdf com ...
Page 253: ...kkap8 pm6 30 06 2006 07 04 238 www EngineeringBooksPdf com ...
Page 265: ...LKAP9 PM6 30 06 2006 07 04 250 www EngineeringBooksPdf com ...
Page 266: ...Programming Q Parameters 10 MKAP10 PM6 30 06 2006 07 04 251 www EngineeringBooksPdf com ...
Page 297: ...MKAP10 PM6 30 06 2006 07 04 282 www EngineeringBooksPdf com ...
Page 298: ...Test Run and Program Run 11 NKAP11 PM6 30 06 2006 07 04 283 www EngineeringBooksPdf com ...
Page 312: ...MOD Functions 12 Okap12 pm6 30 06 2006 07 04 297 www EngineeringBooksPdf com ...
Page 332: ...Tables and Overviews 13 Pkap13 pm6 30 06 2006 07 04 317 www EngineeringBooksPdf com ...