AIR-TO-WATERHEATPUMP MAINTENANCE
121
Method of Testing IPM Module Short Circuit:
(1). Preparation before test: prepare a universal meter and turn to its diode option,
and then remove the wires U, V, W of the compressor after it is powered off for
one minute.
(2). Testing Steps
Step 1: put the black probe on the place P and the red one on the wiring terminal
U, V, W respectively as shown in the following figure to measure the voltage
between UP, VP and WP.
Step 2: put the red probe on the place N and the black one on the wiring terminal
U, V, W respectively as shown in the following figure to measure the voltage
between NU, NV and NW.
(3). If the measured voltages between UP, VP, WP, NU, NV, NV are all among
0.3V~0.7V, then it indicates the IPM module is normal; If any measured valve is
0, it indicates the IMP is damaged.
Summary of Contents for SXVD200LCJ/A-K
Page 1: ...Air to Water Heat Pump Service Manual T1 R410A 50Hz GREE ELECTRIC APPLIANCES INC OF ZHUHAI...
Page 3: ...GREE COMMERCIAL AIR CONDITIONERS AIR TO WATER HEAT PUMP PRODUCT...
Page 15: ...GREE COMMERCIAL AIR CONDITIONERS AIR TO WATER HEAT PUMP CONTROL...
Page 69: ...GREE COMMERCIAL AIR CONDITIONERS AIR TO WATER HEAT PUMP INSTALLATION...
Page 81: ...AIR TO WATER HEAT PUMP INSTALLATION 76...
Page 107: ...GREE COMMERCIAL AIR CONDITIONERS AIR TO WATER HEAT PUMP MAINTENANCE...
Page 117: ...AIR TO WATERHEATPUMP MAINTENANCE 111 6 Temperature sensor error 7 Communication Malfunction E6...
Page 121: ...AIR TO WATERHEATPUMP MAINTENANCE 115 3 1 3 Trip Fig 3 1 3 Flowchart of trip diagnosis...
Page 148: ...AIR TO WATERHEATPUMP MAINTENANCE 142 Indoor Unit 1 Front panel assy Fig 2 Fig 1 Fig 2...
Page 153: ...AIR TO WATERHEATPUMP MAINTENANCE 147 Exploded View of GRS CQ8 0Pd Na k O and GRS CQ10Pd Na K O...