GMC-I Messtechnik GmbH
85
❑
Suppressing Test Steps
Depending on the selected test standard, some of the following
test steps can be suppressed:
1
Before switching line voltage to the device under test, a short-circuit test
is conducted regardless of this setting.
❑
Setting Measuring Parameters for Individual Test Steps
Depending on the selected test standard, some of the following
test steps can be selected:
1
Feature G01
2
Feature G02
❑
Selecting Between Single and Multiple Measurement for Individual Test
Steps
❑
Setting Measurement Duration for Individual Test Steps
Testing time for the respective measurement can be influenced
with these parameters. If a test step for a single measurement is
involved, the entire test step has a duration of the time entered in
seconds. If a test step for a multiple measurement is involved, the
measurement duration for each measuring point is influenced.
If 0 seconds is selected, continuous measurement is conducted
which can only be ended by pressing a key.
1
In the case of test sequence VDE 0701-0702-PRCD with a setting of
“PRCD type: PRCD (SPE)”, measurement duration
cannot
be influenced.
The measurement duration which has been set here only affects the
RPE measurement with PRCD types “PRCD (standard)” and “PRCD-S
(SPE)”.
Parameter
Suppressible test steps
Visual inspection (1)
Visual inspection, standard
Visual inspection 2
Visual inspection, function test, welding units
Function test
Function test
RPE
Protective conductor resistance test
RINS PCI+II
Insulation resistance tests for PCI and PCII
RINS pri./sec.
Insulation resistance test between the primary and sec-
ondary sides of PCIII DUTs
RINS sec./PE
Insulation resistance test between the secondary side and
PE of PCIII DUTs
Polarity reversal
All leakage current measurements with reversed polarity
IPE measurement type
(active)
Protective conductor current test
IT
Touch current test
IT welding circuit
Touch current test at welding circuit
Display test instructions
Test instructions which are not necessarily required for experi-
enced inspectors.
Short-circuit test L-N
Short-circuit test between L and N
1
Short-circuit test LN-PE
Short-circuit test between LN and PE1
1
Open-circuit voltage
(IEC 60974-4)
Open-circuit voltage at welding unit
Continuity test
(VLTG test only)
Continuity test with EL1/VL2E/AT3-IIIE adapter
PCIII supply voltage
Supply voltage measurement (with PCIII DUTs, for mea-
surement type “Active” only)
Parameter
Meaning
RPE IP
Select test current for protective conductor resistance
test: 200 mA AC,
±
200 mA DC, 10 A AC
1
or 25 A AC
2
IPE measurement type
(active)
Set measurement type of the protective conductor current
measurement for the active device test (differential/direct)
IE measurement type
(active)
(IEC 62353)
Set measurement type of the device leakage current mea-
surement for the active device test (differential/direct)
Parameter
Meaning
RPE as
Switch the “protective conductor resistance” test step back
and forth between multiple and single measurement
Parameter
Meaning
RINS PC II as
Switch back and forth between multiple and single mea-
surement for the insulation resistance measurement at
PC II parts (measurements at applied parts and welding
outputs are not affected)
IT as
Switch back and forth between multiple and individual
measurement for the touch current measurement
IT PC II as
(IEC 60974 only) Switch back and forth between multiple
and individual measurement for touch current measure-
ment at PC II parts
Parameter
Meaning
RPE measurement
duration
1
Set testing time for the protective conductor resistance
measurement (0 to 60 seconds)
IPE measurement duration
Set testing time for the protective conductor current mea-
surement (0 to 60 seconds)
IE measurement duration
Set testing time for the device leakage current measure-
ment (0 to 60 seconds)
Parameter
Meaning
IT measurement duration
Set testing time for touch current measurement
(0 to 60 seconds)
IT PC II measurement
duration
(for IEC 60974 only) Set testing time for touch current
measurement at PC II parts (with the exception of welding
outputs) (0 to 60 seconds)
RINS PC II measurement
duration
Set testing time for RINS measurements at PC II parts (0
to 60 seconds)