BCT_T Rev.00 05-2015
pag. 88
5.2.2
– UNPACKING PROCEDURE
All the handling and unpacking operations must be carried out with extreme care, making sure
that all personnel is strictly at a safety distance and that no-one stands under suspended loads,
be they still or in motion.
To unpack the appliance just remove its cardboard wrapping. Take the appliance off the pallet, lifting it by means of a
suitable fork-lift truck; the forks should be placed under the appliance
taking care not to damage the two water tray
runners.
AFTER INSTALLING THE APPLIANCE, WAIT AT LEAST TWO HOURS BEFORE TURNING IT ON.
5.3
– HANDLING THE BLAST CHILLER
5.3.1
– MEANS REQUIRED
See paragraph 5.2.1.
The use of unsuitable equipment can cause accidents to those involved in the operation and/or
damage to the appliance.
The manufacturer declines all responsibility for improper non-compliant use of equipment for
lifting, transport and handling.
5.3.2
– HANDLING THE UNPACKED BLAST CHILLER
All the handling and unpacking operations must be carried out with extreme care, making sure
that all personnel is strictly at a safety distance and that no-one stands under suspended loads,
be they still or in motion.
To move blast chillers on wheels, release the brakes on the wheels and push, taking care to block the brakes again
when the appliance is in its permanent position.
To move blast chillers on feet, lift them with a suitable fork-lift truck; the forks should be placed under the appliance,
taking care not to damage the two water tray runners.
5.4
– BLAST CHILLER ASSEMBLY
The blast chiller is delivered to the customer assembled in all its parts.
Remove the water tray from the chamber and place it in position along the runners placed under the appliance between
the feet.