Maintenance - Checking - Cleaning
GEDA
®
MINI 60 S / MAXI 120 S / MAXI 150 S
Assembly and Operating Manual
74 / 90
BL068 GB Edition 03/2015
8.3.6
Check the support elements and attachment devices
Check the supporting elements, such as the tilting arm, triangular
frame, pivot arm and pivot arm bracket for corrosion, cracks and dam-
age.
Check the bolts of the attachment clamps on the triangular frame, pivot
arm and pivot arm bracket for correct seating.
Pipe clamps 1 ½
″
Torque =
50 Nm [37 lbf ft]
width across flats (AF) = 22 mm
8.3.7
Load carrying equipment
Checking intervals
Load carrying equipment must be checked by a competent person at in-
tervals of no more than
one year
(refer to the national regulations).
Inspection after special incidents
Load carrying equipment must be subjected to a special check by a
competent person after damage or special incidents that could impair
the load capacity, as well as after repair.
The scope of the special check is determined according to the scope of
damage, the incident or repair.
Inspection procedures
The check before initial commissioning and regular checks are signifi-
cantly visual and function checks.
The following must be inspected
−
The condition of the components and equipment.
−
The intended assembly and use.
−
The completeness and efficacy of the safety equipment.
Test verification must be kept for all checks on load carrying
equipment.