Chapter 9: Troubleshooting
To perform the (Check 5) Reactor Outlet Valve Leak Check
This test checks for leaks at valve V5-R. The flow path is highlighted in
.
1. Ensure that the NDIR is plugged, as described in the
Before You Begin
section.
2. Press the
Reactor Outlet Valve
button to start the test. The Analyzer closes the following valves: V1-R,
V3-R, V5-R, V6-R and V7-SH. The Analyzer opens valves V2-R, V4-R and V7-R.
The Gas Control Module pressurizes the lines for 24 sec., and then valve V1-GD closes to trap the
pressure in the area being tested. The system holds for an additional 15 sec. If a major leak is detected
at this time, an "Analyzer failed to pressurize" warning appears and the test will end. During this 39-sec.
pressurization period, the timer remains at 00:00 and "Pressurizing . . ." appears under the timer.
3. When the system passes pressurization, the leak check begins, the timer starts, and "Testing . . ."
appears under the timer. The test lasts for 60 sec. The test passes if the drop in pressure is <= 2.0 psi.
4. If the test fails, but all previous Leak Tests passed, the seal in V5-R may need to be replaced.
5. To continue the series of gas leak checks, leave the plug on the NDIR end cap outlet gas line and
“To perform the (Check 6) Gas-Liquid Separator, NDIR Filter, NDIR Sample
Otherwise, remove the plug for normal operation.