Calibrations
Calibration should be performed on a regular
basis to ensure optimum performance.
A complete calibration procedure
consists
of the following steps:
1.
Offset calibration
, with a buffer solution
(a solution with a very accurate and stable
pH-value) having a pH-value in the range
of pH 6.5-7.5, followed by:
2.
Slope calibration
with a buffer solution
having pH-value that differs at least 2 pH-
units from the buffer used for offset cali-
bration.
Calibration schedule:
An
Offset calibration
should be per-
formed after one month in operation and
then every third month to verify the
performance.
A
Complete calibration
procedure
should be performed at installation and
then every 12 months.
Offset Calibration:
1.
Make sure there is no flow or fluid in the
AK 95 S. The inlet water must be closed.
2.
Start the AK 95 S, enter the
Service
menu and select
Calibrations
.
3.
Select
Transducer
,
External
and
pH TRANSDUCER
from the selection
diagram.
4.
Press
to start calibration routine.
5.
Remove the pH sensor from the pH sensor
housing by loosening the nut holding the
pH sensor and rinse the sensor in distilled
water.
6.
Check that the “REF SET” on the AK 95 S
displays pH 7.
pH transducer calibration
7.
Put the pH sensor in a cup with pH 7
buffer solution (ordering no. 100 810 001)
which must cover the glass membrane i.e.
the level in the cup should be at least
30mm from the bottom.
8.
Stir in order to achieve balance in the
buffer solution. Do not let the pH sensor
lean against the bottom of the cup.
Wait for 2 minutes.
9.*
Press
to set the “REF SET” value on
the AK 95 S and wait until the calibration
display returns.
10.
Press
START
UF
STOP
to load the calibration value
into the EEPROM.
11.
Clean the pH-sensor in RO-water.
Remount the pH sensor into the
pH sensorhousing.
Summary of Contents for AK 95 S
Page 1: ...AK 95 AK 95 S Service Manual A better way to better care...
Page 5: ...This page is intentionally left blank...
Page 6: ...Installation Guide AK 95 AK 95 S January 2004...
Page 7: ......
Page 20: ......
Page 102: ...Maintenance Manual AK 95 AK 95 S October 2006 GAMBRO...
Page 103: ......
Page 125: ...5 22 MaintenanceManual AK95 AK95SHCEN12189Rev 10 2006 This page is intentionally left blank...
Page 126: ......
Page 152: ...Spare Parts List AK 95 AK 95 S October 2005...
Page 153: ......
Page 159: ...HCEN9094Rev 10 2005 7 3 Operator s panel 9 1 3 4 5 6 5 7 5 2 8 6 6 8...
Page 161: ...HCEN9094Rev 10 2005 7 4 Blood pump 10 2 8 3 5 9 4 7 1 6 11 12...
Page 163: ...HCEN9094Rev 10 2005 7 5 Blood pump Motor unit 8 7 6 9 2 10 3 4 5 1 11...
Page 165: ...HCEN9094Rev 10 2005 7 6 Heparin pump 1 2 3 4 5 6 8 7...
Page 169: ...HCEN9094Rev 10 2005 7 8 Magnetic Clamp unit 1 2 3 7 8 12 16 4 5 6 9 10 11 17 18 14 13 19 15...
Page 181: ...HCEN9094Rev 10 2005 7 13 Heater Flow guard 3 9 1 2 10 4 8 7 11 12 13 5 6 3...
Page 189: ...HCEN9094Rev 10 2005 Protective Protective 7 17 Boards 7 1 2 9 6 5 4 3 8...
Page 191: ...HCEN9094Rev 10 2005 1 7 18 Rear box 6 3 7 5 4 2...
Page 195: ...HCEN9094Rev 10 2005 T12AH 250AC BACH BACO HALT 7 20 AC DC 2 4 5 1 6 7 8 9 3...
Page 205: ...HCEN9094Rev 10 2005 7 25 MM I O board 3 2 9 4 6 7 8 5 1 10...
Page 215: ...HCEN9094Rev 10 2005 7 30 UFD Option 4 5 7 17 12 9 6 18 1 6 11 16 8 10 6 13 14 3 2 6 19 15...
Page 219: ...HCEN9094Rev 10 2005 7 32 Boards and Cablings EN1107 10 Step driver board...
Page 221: ...HCEN9094Rev 10 2005 7 32 Boards and Cablings EN1107 10 Step driver board...
Page 224: ......
Page 225: ...9 1 HCEN9160 Revision10 2005 Service Manual Symbols Chapter9 SymbolDescription...
Page 228: ...9 4 HCEN9160Revision10 2005 Service Manual Symbols Thispageisleftintentionallyblank...
Page 234: ...Replacements 10 6 AK 95 AK95SHCEN12078Rev 10 2005 This page is intentionally left blank...
Page 247: ...AK 95 AK 95 S Service Manual...