No-traffic Area Installation Procedure
Step 1: Prepare excavation to be at least 1 to 2 feet
larger than Fuji Clean system dimensions as listed in the
Design Specification Table on page 7 of this Manual.
Important Note: Total height from tank top to grade
should not exceed 24”.
Step 2. Prepare 4”- 6” bed of stone (1/8”), compact
sand, poured or precast concrete level to within 1/8”
per 2 feet. (10mm per 2 meter or 1/200).
Unloading Instructions:
Upon delivery, inspect Fuji clean tank, both outside and inside for possible damage incurred
during transport. If you find damage, or have a question, please contact your distributor
immediately.
9
Compact stone or sand
Use ALL 4-point lifting lugs
Step 3: Carefully lower and set tank.
Level to within 1/8” per 2 feet.
(10mm per 2 meter or 1/200).