Commissioning procedure
CAUTION
To avoid damage caused by uncushioned movement
into the end positions, during
- the first commissioning
- after adjusting the fixed stops
- after adjusting the DIL switches
- or after replacing components and/or tubing
proceed as follows:
1. Make sure that:
•
the compressed air and power supply to the
SPC-10 are switched off
•
the DIL switches are set correctly
•
there is an 0-signal at inputs A and B
•
the maximum mass load is placed on the slide
•
the fixed stops are fitted correctly.
2. Switch on the power supply to the SPC-10.
The SPC-10 will then be initialized (duration approx.
3 seconds). Any modified DIL switch settings will
become effective. In this case the ERROR LED will
flash (out for long period).
3. Then switch on the compressed air supply (5 to 7
bar). As the valve slide assumes the electrical mid-
position, the slide can move slowly into one of the
end positions due to the asymmetrical voltage-press-
ure curve of the proportional directional control
valve.
4. Commissioning
4-6
SPC-10 9902a
Summary of Contents for SPC-10 Series
Page 1: ...Smart Soft Stop SPC 10 Electronic Pneumatic ...
Page 3: ...Order no 170 363 Title Manual Designation P BE SPC10 GB II SPC 10 9902a ...
Page 9: ...VIII SPC 10 9902a ...
Page 10: ...Chapter 1 Summary of system 1 Summary of system SPC 10 9902a 1 1 ...
Page 18: ...Chapter 2 Fitting 2 Fitting SPC 10 9902a 2 1 ...
Page 19: ...Contents 2 Fitting 2 1 Fitting the SPC 10 2 3 2 Fitting 2 2 SPC 10 9902a ...
Page 22: ...Chapter 3 Installation 3 Installation SPC 10 9902a 3 1 ...
Page 52: ...Chapter 4 Commissioning 4 Commissioning SPC 10 9902a 4 1 ...
Page 62: ...Chapter 5 Diagnosis and error treatment 5 Diagnosis and error treatment SPC 10 9902a 5 1 ...
Page 74: ...Appendix A Technical appendix Technical appendix SPC 10 9902a A 1 ...