Figure 5-8: Purge Power and Alarm Entry Point Connections
A. SV1
B. Power
C. Bypass
D. To purge solenoid
E. To be run separately from other cables looms
F. To PT100 sensor
Note
Purge control system power and alarm contact to be directly wired into purge control unit
by end user. The cables must use cable glands suitable for the zone of application of the
analyzer for entry into the analyzer enclosure and the purge control unit.
Terminal
Function
L
Purge control supply (live)
N
Purge control supply (neutral)
K1 (normally open)
Alarm contract
K2 (normally closed)
Alarm contract
Electrical protection for the instrumentation circuitry of the analyzer is provided by fuses
F1 and F2 located inside the analyzer. Refer to
.
The customer supplied power cable for the analyzer instrumentation will be connected to
terminals 1 - 3.
Reference Manual
Install
00809-0100-4512
October 2019
Reference Manual
59
Summary of Contents for Rosemount CT5100
Page 16: ...16 ...
Page 20: ...Contents Reference Manual October 2019 00809 0100 4512 xx Rosemount CT5100 Ex ...
Page 28: ...Theory of operation Reference Manual October 2019 00809 0100 4512 28 Rosemount CT5100 Ex ...
Page 46: ...Specifications Reference Manual October 2019 00809 0100 4512 46 Rosemount CT5100 Ex ...
Page 66: ...Install Reference Manual October 2019 00809 0100 4512 66 Rosemount CT5100 Ex ...
Page 84: ...Start up procedure Reference Manual October 2019 00809 0100 4512 84 Rosemount CT5100 Ex ...
Page 92: ...Shutdown procedure Reference Manual October 2019 00809 0100 4512 92 Rosemount CT5100 Ex ...
Page 112: ...Gas calibration Reference Manual October 2019 00809 0100 4512 112 Rosemount CT5100 Ex ...