8.1
Fitting the dongle box
Fig. 23: Dongle-Box
1
Connection wire for connection to input II of the pump
2
Dongle Box eg. MicroFlow-Box
V
input for oval gear meter
VI
Fixed connector cable for connecting the pulse input to
the EMP pump (input II)
VII input for batch pulse and metering lock
VIII input for pulse, standard signal input and metering lock
Fig. 24: Fitting the Dongle-Box and Micro-Flow-Box
1.
Fit the Dongle Box eg. MicroFlow-Box (Fig. 23) to the rail of the EMP pump provided
for this purpose (Fig. 24, pos. A).
2.
Slide the Dongle Box eg. MicroFlow-Box (Fig. 23) onto the rail on the left side of the
EMP pump (Fig. 24, pos. A), until it snaps into place.
3.
Connect the connection cable (Fig. 23, pos. 1 and
, pos. 2) to the
input for pulse / standard signal (Fig. 24, pos. 1).
4.
Switch the pump off and afresh on.
The additional functions in the metering pump electronics can thus be activated and
executed.
NOTICE!
If, before upgrading with a Dongle Box eg. MicroFlow-Box a plug is connected
to the input for pulse / standard signal (Fig. 24), then this plug can be
connected after the upgrade to plug VIII (Fig. 23) of the Dongle Box eg.
MicroFlow-Box.
Upgrading the EMP KKS E60 to the EMP KKS E60PLUS
49
417101442 Rev. 12-02.2019
Summary of Contents for Elados EMP KKS E60
Page 2: ......
Page 123: ...14 2 Abmessungen Abb 89 Abmessungen Technische Daten 121 417101442 Rev 12 02 2019 ...
Page 135: ......
Page 258: ...14 2 Dimensions Fig 90 Dimensions Technical Specifications 122 417101442 Rev 12 02 2019 ...
Page 393: ...14 2 Dimensions Fig 93 Dimensions Données techniques 123 417101442 Rev 12 02 2019 ...
Page 405: ......