Test Operation
SiUS39-601
64
Test Operation
1.
Test Operation
1.1
Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply on
1.1.2 Turn Power on
Turn outdoor unit power on.
Carry out field setting on
outdoor PC board
Turn indoor unit power on.
(V3056)
{
Be sure to turn the power on 6 hours before starting operation to protect
compressors. (to power on clankcase heater)
{
For field settings, refer to “Field Settings” on and after P81.
After the completion of field settings, set to “Setting mode 1”.
Summary of Contents for BSVQ36MVJU
Page 115: ...Field Setting SiUS39 601 104 Test Operation ...
Page 227: ...Troubleshooting OP Unified ON OFF Controller SiUS39 601 216 Troubleshooting ...
Page 231: ...Piping Diagrams SiUS39 601 220 Appendix 1 Piping Diagrams 1 1 Outdoor Unit RXYQ72M 96M ...
Page 236: ...SiUS39 601 Wiring Diagrams for Reference Appendix 225 RXYQ144 168 192MTJU C 3D050353A ...
Page 249: ...Example of Connection SiUS39 601 238 Appendix ...
Page 265: ...Precautions for New Refrigerant R 410A SiUS39 601 254 Precautions for New Refrigerant R 410A ...
Page 269: ...SiUS39 601 iv Index ...