Procedure
1. Review the contents of the displayed screen.
2. When all information is correct, click Next.
The "Complete" screen displays.
13.6 Review the Complete Screen
Prerequisites
ClusterStor L300 and L300N configuration has been completed.
About this task
The Complete screen confirms the configuration process is complete and the storage cluster is operational.
Procedure
1. To finish the process, click Continue to exit the first-run configuration and proceed to CSM.
2. Start the Lustre file system.
This step can be performed either on the primary MGMT node (via CLI) or CSM.
a. From the primary MGMT node:
[MGMT0]$
cscli mount -f file_system_name
Sample output:
[admin@dvtrack00 ~]$
cscli mount -f testfs
mount: MGS is starting...
mount: MGS is started!
mount: testfs is started on dvtrack[02-03]!
mount: testfs is started on dvtrack[04-05]!
mount: testfs is started on dvtrack[06-07]!
mount: File system testfs is mounted.
[admin@dvtrack00 ~]$
-OR-
b. From CSSM, perform the following:
1. Click the Node Control tab.
2. Select Nodes in FS
fsname
(which is usually the default).
3. Click All Nodes in Filter menu tab.
4. Select Start Lustre from the drop-down menu.
3. CSM starts and the ClusterStor L300 and L300N system is ready for use.