Burner Operation and Control
2-4
750-91 (revised 2009)
Model CB-LE Packaged Boiler Manual
2.4 — Controls for Gas Firing
Depending upon the requirements of the insurance carrier or other governing agencies, the gas flow control sys-
tem, or gas train, may consist of some, or all, of the items listed below.
Indicator Lights
Provide visual information of boiler operation as follows:
•
Flame Failure
•
Load Demand
•
Fuel Valve (valve open)
•
Low Water
Program Relay and Flame Safeguard Control
Automatically programs each starting, operating, and shutdown
period in conjunction with operating limit and interlock devices.
Includes, in a timed an proper sequence, the operation of the blower
motor, ignition system, fuel valve(s), and the damper motor. The
sequence includes air purge periods prior to ignition and upon
burner shutdown.
The flame detector portion of the control monitors both oil and gas
flames and provides protection in the event of loss of a flame signal.
The control recycles automatically during normal operation, or fol-
lowing a power interruption. It must be manually reset following a
safety shutdown caused by a loss of flame. An internal checking cir-
cuit, effective on every start, prevents burner operation in the event
anything causes the flame relay to hold in during this period.
Component
Description
Gas Pilot Valve
A solenoid valve that opens during the ignition period to admit fuel
to the pilot. It closes after main flame is established. The sequence
of energizing and de-energizing is controlled by the programming
relay. A second gas pilot valve may be required by insurance regula-
tions.
Gas Pilot Vent Valve
When a second gas pilot valve is required, a normally open vent
valve (optional equipment) is installed between them. Its purpose is
to vent gas to the atmosphere, should any be present in the pilot
line when the pilot valves are closed. The valve closes when the
pilot valves are energized.
Gas Pilot Shutoff Cock
For manually opening or closing the gas supply to the gas pilot
valve.
Gas Pressure Gauge
Indicates gas pressure to pilot.
Gas Pressure Regulating Valve
Reduces incoming gas pressure to suit the pilot.
Gas Pilot Aspirator
Provides complete mixing of gas and air to the pilot.
Gas Pilot Adjusting Cock
Regulates the size of the gas pilot flame.
Component
Description
Summary of Contents for CBLE
Page 14: ...xiv 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 48: ...Burner Operation and Control 2 22 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 64: ...Waterside Care and Requirements 3 16 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 72: ...Sequence of Operation 4 8 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 158: ...Inspection and Maintenance 8 38 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 166: ...Parts 9 8 750 91 revised 2009 Model CB LE Packaged Boiler Manual Control Panel...
Page 168: ...Parts 9 10 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 7 Front Head Electrical...
Page 170: ...Parts 9 12 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 9 Front Head Insulation...
Page 174: ...Parts 9 16 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 12 Light Oil Air Piping...
Page 176: ...Parts 9 18 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 13 Heavy Oil Air Piping...
Page 182: ...Parts 9 24 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 16 IFGR Impeller...
Page 184: ...Parts 9 26 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 18 Temperature Controls...
Page 186: ...Parts 9 28 750 91 revised 2009 Model CB LE Packaged Boiler Manual W C Main Aux...
Page 193: ......
Page 194: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...