Inspection and Maintenance
8-32
750-91 (revised 2009)
Model CB-LE Packaged Boiler Manual
Therefore, before assuming that the refractory requires reworking:
1. Check the condition of the tadpole gasket.
2. Check for cracks in the castable refractory.
3. Check the tightness of the door bolts.
4. See that the air line to the sight tube is clear, and that the connections are tight. If necessary, blow the line clear
with an air hose.
It is normal for refractories exposed to hot gases to develop thin “hairline” cracks. It by no means indicates improper
design or workmanship. Since refractory materials expand and contract with changes in temperature, they should be
expected to show minor cracks due to contraction when examined at low temperatures. Cracks to approximately 1/
8" across may be expected to close at high temperature. If there are any cracks that are relatively large (1/8" to 1/4"
in width), clean and fill them with high-temperature-bonding mortar.
If the refractory or blanket insulation require replacement, contact your local Cleaver-Brooks authorized
representative.
A good seal between the rear door and the pressure vessel is necessary to prevent leakage of combustion gases, loss
of heat, and to aid in obtaining operating efficiency. Leaks can also cause hot spots that can lead to premature
refractory failure and/or damage to the door metal.
Figure 8-16 Rear door seal
1. Tadpole gasket
2. Rope 1-1/2” dia.
3. Blanket insulation 1/2” x 2”
Summary of Contents for CBLE
Page 14: ...xiv 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 48: ...Burner Operation and Control 2 22 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 64: ...Waterside Care and Requirements 3 16 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 72: ...Sequence of Operation 4 8 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 158: ...Inspection and Maintenance 8 38 750 91 revised 2009 Model CB LE Packaged Boiler Manual...
Page 166: ...Parts 9 8 750 91 revised 2009 Model CB LE Packaged Boiler Manual Control Panel...
Page 168: ...Parts 9 10 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 7 Front Head Electrical...
Page 170: ...Parts 9 12 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 9 Front Head Insulation...
Page 174: ...Parts 9 16 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 12 Light Oil Air Piping...
Page 176: ...Parts 9 18 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 13 Heavy Oil Air Piping...
Page 182: ...Parts 9 24 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 16 IFGR Impeller...
Page 184: ...Parts 9 26 750 91 revised 2009 Model CB LE Packaged Boiler Manual 9 2 18 Temperature Controls...
Page 186: ...Parts 9 28 750 91 revised 2009 Model CB LE Packaged Boiler Manual W C Main Aux...
Page 193: ......
Page 194: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...