Chapter 8: Acceptance & Commissioning Procedures
PTP 820 Commissioning Log
phn-3962 004v000
Page 8-12
Mounting losses:
4. LINK PARAMETERS
Site 1
Site 2
Link distance:
Rain zone:
Expected RSL (dBm):
Expected Diversity RSL (dBm):
RSL Main (dBm):
RSL Diversity (dBm):
Deviation from exp?
RSL ≤4
dB?
5. COMMISSIONING TESTS
Site 1
Site 2
Line loopback:
Pass
Pass
ODU loopback:
Pass
Pass
Radio BER:
Pass
Pass
FE test:
Pass
Pass
GbE test:
Pass
Pass
6. MANAGEMENT
CONFIGURATION
Site 1
Site 2
Eth IP Address:
Eth IP mask:
Default router:
In-band VLAN
7. REMARKS/NOTES
8. INSTALLATION INFORMATION
Installed by:
Name:
Company:
Date:
Signature:
Commissioned by:
Name:
Company:
Date:
Signature: