PTP 800 Series User Guide
I nst alling t he I F and ground cables
phn- 2513_004v000 ( Oct 2012)
5- 59
To run the IF cable into the building, proceed as follows:
1
Make an entry point into the building and run the main IF cable into the
building.
2
Ground the IF cable to the external ground bar outside the building entry point,
as described in
Making an IF cable ground point
3
Install the bottom LPU inside the building entry point.
4
Ground the bottom LPU to the master ground bar.
5
Cut any surplus length from the bottom end of the main IF cable and fit an N
type connector, as described in
Fitting an N type connector to an IF cable
6
Connect the main IF cable (from the ODU) to the SURGE port of the bottom LPU.
7
Connect the LPU-CMU IF cable to the EQUIPMENT port of the bottom LPU and
run it to the location of the CMU.
Summary of Contents for PTP 800 Series
Page 1: ...Cambium PTP 800 Series User Guide System Release 800 05 02 ...
Page 40: ...Licensing requirements About This User Guide 10 phn 2513_004v000 Oct 2012 ...
Page 232: ...Limit of liability Chapter 3 Legal information 3 22 phn 2513_004v000 Oct 2012 ...
Page 322: ...Radiation hazard assessm ent Chapter 4 Reference information 4 90 phn 2513_004v000 Oct 2012 ...
Page 428: ...Replacing IRFU components Chapter 5 Installation 5 106 phn 2513_004v000 Oct 2012 ...
Page 630: ...Using recovery mode Chapter 7 Operation 7 78 phn 2513_004v000 Oct 2012 ...