Commissioning report
B
Confirm commissioning as complete; sign and date the
report.
Commissioning tasks
Page Actual values
Comments
1.
Fill the heating system and check for leaks
24
2.
Have the details regarding water quality in the operator's log
been observed?
Yes:
- Levels of concentration of additives
Additives:
_________
Levels of
concentration:
_______%
3.
Record gas parameters: Wobbe index
Calorific value
30
_________ kW/m³
_________ kW/m³
4.
Check the gas pipe for tightness
29
– Vent gas line
31
5.
Create operating pressure
28
6.
Check the ventilation and extract air apertures and the flue
connection
31
7.
Check the system equipment level
30
8.
Commission the control unit and burner
32
9.
Adjust gas type if required
31
10.
Record actual values:
35
Full load
Partial load
- Draught
_______Pa
_______Pa
- Gross flue gas temperature t
A
______ °C
______ °C
- Air temperature t
L
______ °C
______ °C
- Net flue gas temperature t
A
- t
L
______ °C
______ °C
- Carbon dioxide content (CO
2
) or oxygen content (O
2
)
_______ %
_______ %
Flue gas losses q
A
_______ %
_______ %
- CO value, free of air
_____ ppm
_____ ppm
11.
Test the gas supply pressure
33
____________ mbar
12.
Check for leaks during operation
36
13.
Function checks
36
– Check ionisation current
____________ μA
14.
Install casing parts
37
15.
Inform operator; hand over technical documentation
37
16.
Correct commissioning by the installing contractor
Signature:______________________
17.
Operator signature
Signature:______________________