Page 95
Brute Elite Boilers and Water Heaters
Section 12
troUBleSHootInG
12.1 Potential Setup and
Synchronization Problems
Because the Brute Elite uses a sophisticated control
system, it can constantly perform a series of self-
checks. For example, as a burner is lighted, the
controller checks each stage of the purge and
ignition process. If part of the process does not
happen on time, or takes too long to occur, the
controller stops the process. We have detailed these
self-checks in the section on “Operating Sequence.”
Two of these self-checks are particularly important:
• Controller synchronization
• Flap valve status
If the control system is not satisfied with the results
of both of these checks, it will not allow the system
to run. Sometimes the reason for this may not be
obvious at first – that’s why we are describing them
at the start of this section on Troubleshooting.
Operator
interface
Boiler 1
Slave 4
Boiler 2
Slave 3
Slave 2
Lead Lag
Master and
Slave 1
Slave 6
Boiler 3
Slave 5
Slave 8
Boiler 4
Slave 7
Addr
1
Addr
2
Addr
3
Addr
4
Addr
5
Addr
6
Addr
7
Addr
8
fig. 122 – lead/lag arrangement in a multiple-Boiler Installation
12.1.1 Controller Synchronization
On a multiple-boiler installation, the individual
boiler controllers are arranged in a “daisy chain”
using a Modbus connection, with the Secondary
control of one boiler connected to the Primary
control of the next boiler. Up to four boilers, with
up to eight controllers, can be connected in this way.
See Fig. 122.
As part of the setup process, each of these
controllers must be given a unique address. (For
details, see Section 9 - Installation and Setup.” The
controls must be set up and addressed correctly
before the Modbus wiring is completed. If the wiring
is attached before the Modbus control addresses are
changed, there will be multiple controls with the
same address, and
the system will not work.
When a Lead/Lag system is first powered up, the
controller acting as the Lead/Lag Master goes
through a “synchronization” process. During
synchronization, the controller establishes
communications with each of the Slave controllers
via the Modbus link. The Slave controllers
download some setup parameters and operating
history information. (On a system with several
boilers, this phase can take several minutes.) If the
Master cannot establish communications with one of
the Slaves, it triggers a Hold or Lockout.
Summary of Contents for BNTH1000
Page 2: ...Bradford White Corp...
Page 12: ...Page 8 Bradford White Corp Fig 6 Dimensions BNT 1700...
Page 38: ...Page 34 Bradford White Corp Fig 21 Ladder Diagram...
Page 39: ...Page 35 Brute Elite Boilers and Water Heaters Fig 22 Wiring Diagram...
Page 40: ...Page 36 Bradford White Corp...
Page 52: ...Page 48 Bradford White Corp Fig 51 Connection Terminals...
Page 130: ...Page 126 Bradford White Corp Fig 141 Rear Panel BNT1000 Fig 142 Rear Panel BNT1700...
Page 131: ...Page 127 Brute Elite Boilers and Water Heaters Fig 143 Machine Frame BNT1700...
Page 132: ...Page 128 Bradford White Corp Fig 144 Front Panels and Covers BNT1000 and BNT1700...
Page 133: ...Page 129 Brute Elite Boilers and Water Heaters Fig 145 Burners and Combustion Chamber BNT1000...
Page 134: ...Page 130 Bradford White Corp Fig 146 Burners and Combustion Chamber BNT1700...
Page 136: ...Page 132 Bradford White Corp Fig 149 Burner Detail BNT1700...
Page 139: ...Page 135 Brute Elite Boilers and Water Heaters This page intentionally left blank...
Page 140: ...Page 136 Bradford White Corp This page intentionally left blank...