Page 74
Bradford White Corp.
Required tools: Screwdrivers, Torx bits, combustion
analyzer
In the rest of this section we will explain the setup
procedure in more detail.
1. On the gas valve for the Primary burner on the
boiler, locate the adjustments for the high fire
CO
2
and low fire CO
2
. See Fig. 98 and 99.
Table 17 lists the CO
2
readings you should see
at high fire and low fire.
2. To start the setup, turn on the call for heat.
3. Before you can set up the Primary burner, you
must shut off the Secondary burner. Go to the
Home screen on the display. Press the icon for
the control labeled Secondary.
fig. 100 – Home Screen
4. The system will present the Status Summary
screen.
fig. 101 – Status Summary Screen
5. Press the Operation button. The system will
present the Operation screen for the Secondary
burner.
fig. 102 – operation Screen
Press the Burner Enable switch in the upper
left-hand corner of the screen. Since you
selected the Secondary control for this boiler,
this will turn off the Secondary burner. The
system will ask you to log in as you do this.
6. Now you can work with the Primary burner
for this boiler. Press the Home icon to go back
to the Home screen on the display (Fig. 100).
Press the icon for the control labeled Primary.
7. The system will present the Status Summary
screen for the Primary burner. Press the
Operation button.
8. The system will present the Operation screen
for the Primary burner.
fig. 103 – operation Screen
Model
Gas Type
High Fire CO
2
Low Fire CO
2
Pressure Differential
1,000
Natural
8.5% ± 0.2
0.5% lower than high fire CO
2
0.5” to 1.2” wc*
Propane
9.5% ± 0.2
0.5% lower than high fire CO
2
0.5” to 1.2” wc*
1,700
Natural
9.0% ± 0.2
0.5% lower than high fire CO
2
0.5” to 1.2” wc*
Propane
10.0% ± 0.2
0.5% lower than high fire CO
2
0.5” to 1.2” wc*
* - Only check the pressures if there are problems getting the CO
2
and CO values in range.
table 17 – Co
2
range and Pressure Differential
Summary of Contents for BNTH1000
Page 2: ...Bradford White Corp...
Page 12: ...Page 8 Bradford White Corp Fig 6 Dimensions BNT 1700...
Page 38: ...Page 34 Bradford White Corp Fig 21 Ladder Diagram...
Page 39: ...Page 35 Brute Elite Boilers and Water Heaters Fig 22 Wiring Diagram...
Page 40: ...Page 36 Bradford White Corp...
Page 52: ...Page 48 Bradford White Corp Fig 51 Connection Terminals...
Page 130: ...Page 126 Bradford White Corp Fig 141 Rear Panel BNT1000 Fig 142 Rear Panel BNT1700...
Page 131: ...Page 127 Brute Elite Boilers and Water Heaters Fig 143 Machine Frame BNT1700...
Page 132: ...Page 128 Bradford White Corp Fig 144 Front Panels and Covers BNT1000 and BNT1700...
Page 133: ...Page 129 Brute Elite Boilers and Water Heaters Fig 145 Burners and Combustion Chamber BNT1000...
Page 134: ...Page 130 Bradford White Corp Fig 146 Burners and Combustion Chamber BNT1700...
Page 136: ...Page 132 Bradford White Corp Fig 149 Burner Detail BNT1700...
Page 139: ...Page 135 Brute Elite Boilers and Water Heaters This page intentionally left blank...
Page 140: ...Page 136 Bradford White Corp This page intentionally left blank...