X7-8-Install-IG100 Installation Guide
Brocade
®
X7-8 Director Hardware Installation Guide
NOTE
Ensure that the captive screws securing the fan and power supply assemblies are tightened. If they are not
tightened, the air pressure inside the chassis may unseat these FRUs from chassis connectors.
Precautions Specific to Power Supply Assembly
Observe the following precautions when replacing the power supply assembly:
NOTE
Depending on the blade configuration of the device and the number of power supplies installed, the device may
be able to continue operating while replacing a power supply. See "Power Supply Requirements" in the
Brocade
X7 Director Technical Specifications
for minimum power supplies required for AC low and high voltage line
operation, redundancy in case of power supply failure, and other specifications. If there is insufficient power, the
device will start powering down blades until the power demand can be met.
NOTE
A device with slots for eight port blades can have up to four power supplies installed. If you are adding additional
power supplies, you can use the procedures in this section under
to install the new
power supplies. Be sure to follow the steps on those procedures to enable sending notifications if the additional
power supplies should fail.
NOTE
Make sure that captive screws securing power supply assemblies to chassis are tightened. If not, high pressure
from fans' operation may unseat power supply assemblies from chassis connectors.
See
for caution and danger notices related to installing power supplies.
Power Supply Assembly Fault Indicators
Use one of the following methods to determine if a power supply is faulty:
•
Check the power supply status LED.
–
The LED may take up to 10 seconds to illuminate. If the LED does not illuminate, the power supply has no incoming
power. Check if the power supply is properly seated in the backplane connector. Check the power source to the
power cord.
–
If the LED is flashing green, the power supply may be faulty.
For more information on LED operation, see
Interpreting Power Supply LEDs
.
•
Enter
psShow
. If the status of power supply displays absent or faulty, check if power supply assembly is seated in
chassis. If it is, the power supply could be faulty.
•
Enter
sensorShow
to determine if a power supply is running above average temperatures of other installed power
supplies.
•
Enter
errDump
to display the system error log. Refer to the
Brocade Fabric OS Message Reference Manual
for more
information on the messages in this log.
See the
and the
Brocade Fabric OS Command Reference Manual
for output examples and
additional information on Fabric OS commands.
For more information on error messages, refer to the
Brocade Fabric OS Message Reference Manual
.
Power Supply Assembly Task Guide
This section contains a guide to more complete, detailed steps in this section for installing or replacing power supply
assemblies when the chassis is running (hot-swap) or must be powered off (cold-swap). References are provided for more
detailed information.
X7-8-Install-IG100
166
Broadcom
Summary of Contents for Brocade X7-8
Page 212: ......