6.2
Measuring the room
If a ‘Parametric’ cycle is to be run then the room volume must be known. If this is
not already known it is recommended to use the optional device available which
will accurately measure the volume of a room, see section 18. For rooms or suites
which are more complicated than a rectangular room it may be necessary to
measure several volumes and add them together.
Ensure no objects (including paper) that might cause blockage of the
air inlet to the left and above the power switch are in the cable
storage area. See section 4.1.1.
Plug the longer power cable into the base unit, and the
other end into an earthed socket, and turn the power
on. Turn on the white switch on the Base unit above the
power connection. The light ring will illuminate.
Ensure
the white switch is not obstructed, as it is the main
disconnect device.
If the ProteQ is to communicate with the building’s
systems then it may be necessary to connect the
interface cables to the voltfree / remote start stop
connectors, see Section 4.1.1.
Plug the shorter cables into the side of the aeration
units, and plug the other end into an earthed electrical
socket. Note - up to three aeration units can be
plugged into the same socket. Do not plug them into
the same socket as the Base unit if supply is 100V or
120V.
Turn on the power at the back of the aeration unit
using the white switch and after a short time the fan
will start, and the wireless indicator will illuminate.
Ensure the white switch is not obstructed, as it is the
main disconnect device.
Remove the wound power cable from the lectern, and
plug the cable into the socket at the lower rear of the
lectern. Plug into an earthed electrical socket, and turn
the power on. The screen will illuminate.