Chapter 3: Configuration and commissioning
74
1X-X3E Series Installation Manual
If any other indicators are on, check your installation thoroughly before
proceeding.
Fault startup
In accordance with EN 54-2, the control panel has a special startup sequence
that is used after an internal fault has been detected by the control panel.
This is indicated as follows:
• The general Fault LED flashes fast
• The System Fault LED flashes slow
When this happens:
1. Enter the operator user level password.
2. Press the Reset button to reset the control panel.
If the fault status persists after reset, the control panel aborts the startup
sequence and turns on the System Fault LED.
When this happens, check all control panel connections and configuration, as
described in “Before commissioning the control panel” on page 73.
Battery startup
To power up the control panel from the batteries, press the battery start button on
the control panel PCB (marked as BAT. START, see Figure 19 below). Keep the
button pressed for approximately 5 seconds.
Figure 19: Battery startup button
Summary of Contents for 1 3E Series
Page 1: ...1X X3E Series Installation Manual P N 501 419303 1 20 ISS 20JUL21 ...
Page 86: ...Chapter 4 Maintenance 80 1X X3E Series Installation Manual ...
Page 106: ...Appendix A Configuration presets 100 1X X3E Series Installation Manual ...
Page 110: ...Appendix B Regulatory information 104 1X X3E Series Installation Manual ...
Page 113: ......
Page 114: ......